logo
  

Russia delays transferring Bushehr plant to Iranian technicians: report
PDF Print E-mail
Font Size Larger Font Smaller Font
c_330_235_16777215_0___images_stories_edim_02_br1(95).jpgTEHRAN – NIAEP-Atomstroyexport, a subsidiary of Russia’s state nuclear agency Rosatom, has announced that transferring the Bushehr nuclear plant to Iranian technicians has been delayed by three months due to technical considerations.
 
Vladimir Pavlov, Atomstroyexport’s deputy director responsible for constructing power plants in Iran and Turkey, told RIA Novosti news agency that the Bushehr nuclear power plant had originally been scheduled to be transferred to Iranian technicians for operation by late December but it will take place in late March 2013.
 
MJH/PA

rssfeed socializeit
Socialize this
Subscribe to our RSS feed to stay in touch and receive all of TT updates right in your feed reader
Twitter Facebook Myspace Stumbleupon Digg Technorati aol blogger google reddit